CenterPoint’s Construction Crews Begin Restoration Work Along Golden Valley Rd

With 100 percent of the natural gas main installed forĀ CenterPoint Energy’s 2018 Belt Line Project, crews are now restoring the areas affected by the construction and expect to finish in October.

Starting Oct 1, crews began restoring the curb along Golden Valley Rd from Lilac Dr N to St Croix Ave N.

During the week of Oct 8, crews will finish the sidewalks and driveway aprons along the Golden Valley Rd construction route andĀ restore the curb along Golden Valley Rd up to Theodore Wirth Parkway.

During the week of Oct 15, crews will restore the blacktop along Golden Valley Rd on the both sides of Highway 100.

For more information or to see past updates, go to CenterPoint Energy’s Golden Valley 2018 Belt Line Project. Or, call CenterPoint Energy’s Information Hotline at 612-321-5369 or Communications Specialist Hannah Gullickson at 612-321-5546.